The Leat Project

The Solution

digtrnch.jpg (28682 bytes)

Restoration required extensive excavation and skilled labour.

 

To repair the Leat, extensive work was required.

Firstly, Rhododendron covered the entire project area.  Although the Trust had already done some clearance, a significant amount still had to be cleared.   Rhododendron is an alien species and renders areas sterile and physically impenetrable.  Its clearance is, in itself, a major task.  This was done by Trust staff, those on Career Contact and volunteers.  The same workforce also carried out all the manual labour required to complete the Leat Project.  This included all the extensive gabion basket work, concreting, stone walling, the installation of the sluice and steel pipes.

The Victorian Leat was damaged in two places.  The worst area of damage had resulted in flood water washing out  a deep ravine.  Thus the line of the Leat now had to descend a sheer drop of 13 metres.  In order to ensure that flood water could be carried safely through this steep gradient it was decided to pipe the Leat for this short distance.  The Ravine was first filled in using two 20 tonne swing shovels.  It then had to be compacted to prevent settlement.  A trench was dug into the compacted soil so that a 42 metre length of steel pipe could be laid.   The pipe was buried and collection and discharge areas constructed.  These were of gabion basket construction, local stone was used for stone walling.  This method of containing the Leat over trouble spots was used in another two sections.   One of 6 metres, the other 18 metres.  Again collection and discharge areas together with stone walling were constructed.

Surveys were carried out by the Forestry Commission Civil Engineers Department from the Somerset and South Devon Forest District and by the contractor Peter Williams.  They revealed an average gradient for the mile long Leat of 1:60. This gradient was ideal, as the resulting water flow was neither too fast to cause erosion, nor too slow so that silting would occur.

Two ponds were also created as part of this substantial project.   At the most northerly upstream part of the reserve, where the valley was narrowest, a large pond, Monument Pond was constructed.  Its purpose was to ensure that all water entering the reserve at this point was collected.  Monument Pond has two outlets.  These outlets are controlled by a sluice.  This ensures that at low water flows, all water goes down stream to the existing wetland habitats.  At times of flood, excess water enters a newly constructed section of Leat.  From here it cascades into a new pond, Dragonfly Pond.  From Dragonfly Pond the only exit is to the original Victorian Leat.  This had been cleaned out and small weirs constructed where necessary.

 

pipes.jpg (66380 bytes)

Delivery of pipes to the Centre.  These will be used to pipe the Leat through the Ravine.

 

survey.jpg (70614 bytes)

Civil Engineer checking levels for Leat excavation

 

monut.jpg (31132 bytes)

Leat Project Contents